Full depot electrification at Arriva’s Palmer’s Green bus depot
ADDCharge installed 50 EV chargers at Arriva’s Palmer’s Green bus depot – 25 indoors, 25 externally – including a freestanding 45-metre steel gantry to carry overhead charger reels inside the depot, delivering the full electrical, civil, and structural steel scope for Zenobe in 26 weeks.
| Client | Arriva |
| Contracted through |
Zenobe |
| Location | Palmer’s Green, London |
| Sector | Bus & Coaches |
| Value | ~£1.16m |
| Duration | 26 weeks on site; approximately 6-8 months inception to handover |
| Scope | Structural steel gantry design and installation, electrical engineering and installation, civil works, indoor and outdoor charger installation, project management |
Palmer’s Green depot needed EV chargers both indoors and outside. Bus depots are designed to maximise vehicle capacity – buses sit 750 millimetres apart, nose to nose and side to side, with barely enough room to move between them. Space is at a premium before a single cable is laid or a single charger is mounted.
The Challenge
How we delivered it
The full scope – structural steel, electrical engineering, civil works, and both indoor and outdoor charger installation – was delivered by ADDCharge from initial scoping through to commissioning. Palmer’s Green is part of an ongoing programme of bus depot EV installation projects ADDCharge has delivered for Zenobe across London.
Key Project Stats
20 Indoor charger reels on gantry
~£1.16m Project value
50 Total EV chargers installed
26 Weeks on site
45m Gantry span
6-8 months Inception to handover
What ADDCharge delivered
Electrical engineering and HV/LV installation
Civil engineering and groundworks
External EV charger installation (25 units)
Structural steel gantry design and installation (45 metres, indoor)
Indoor EV charger installation (overhead reel system, 20 units)
Full project management from initial scoping to commissioning
Ray Adde,
Director, ADDCharge